This week we had the plastering mostly finished, just a few little things to be finished off. The finishing carpenter was working all this week, he is a one man show so that is taking a lot longer then we thought.
|
Plaster on under the stairs |
Most of the skirting boards and the doors are on.
|
Family Room Plastering done |
|
Doors and wardrobe doors on |
|
Doors to main bedroom |
Water proofing was done early in the week in all of the bathrooms.
|
Waterproofing |
All of the outside plumbing was connected, but the Mastic sealant was not put in the articulation joints behind the downpipes on one side of the house, so that will all have to be taken back down and sealed.
We had the laundry sink and one bath delivered, don't know what happened to the other bath, I am sure it will turn up eventually.
On Friday we had the garage doors installed. I think they look great.
|
Back of the Garage |
|
Front garage doors |