I'm sure none of you that have been following this Blog will be surprised to hear that this week didn't go to plan. The fact is, that not a single week has gone to plan since week four of this epic saga.
As Beck said in her last post, these things were to happen this week:
The eave painters were to have painted the upstairs eaves, they didn't.
The downpipes were to have been installed and painted, they weren't.
The Scaffolding was to have been removed, it wasn't.
The downstairs fascia and gutter was to have been installed, it isn't.
And the bloody useless brickies Kurmond have contracted were supposed to have finished, and they aren't.
So that is exactly 0 from 5. And that's not even considering that half of those jobs were supposed to be finished LAST week. Even given the wet weather we've had, the delays are ridiculous and I think a lack of planning and organisation have resulted in the estimated lock-up date going from "by December" to "before Christmas" and now it doesn't look like it will even happen in January. Luckily we didn't hire Kurmond to organise a piss up in a brewery, or we'd all die of thirst.
Anyway, I think it is fairly safe to say that nothing will happen now until next year. So Merry Christmas to you all, and a safe and happy New Year.
D.
The story of building the Glenleigh 39 by Kurmond Homes. Tracking the progress, trials and tribulations of the project from knock down to rebuild.
Friday, December 23, 2011
Tuesday, December 20, 2011
Weekly Update (Day 96) Eaves, cavity sliders, cladding, bricks and brick cleaning
Well on Monday the bricks didn't arrive, but the carpenters did. They put on the eaves, the cladding outside of bedroom 4, installed the cavity sliders, put in the frame work for the ducting and the frame work for the niche in the main bedroom. The carpenters are very young (Derrick thought they were trying to pinch stuff), but these guys did such a great job. We went around to check all of the brick ties, to see if they had missed any and in the whole house we only found one that they missed. Every thing they told us they would do, they did.
On Tuesday the bricks arrived, but they are not the same colour.
Wednesday the brickies turn up. I go out to site on Wednesday afternoon thinking all of the brick work would have been finished, but it isn't. They have run out of bricks AGAIN.
They finished the front of the garage, one side and the front of the balcony and above the front door. Instead of using the different coloured bricks on the balcony and the garage ( these will be done in moroko, so you won't see the colour of the bricks) they used the correct colour bricks on these to spots and used the different coloured ones above the front door. Around the front door should be face bricks, but now there is the two different colours. Our SS told us they can be colour matched and we won't be able to tell.
Thursday the bricks were cleaned and that makes such a big difference to the look of the house.
Derrick has a meeting with the SS tomorrow. The painters should be there to do any painting on the top level before the scaffolding is taken down. (Oh and the brickies are supposed to be back Wednesday - We will see)
Beck
| Cladding on Bedroom 4 |
| Cavity sliders into the Media Room |
| Niche in Main bedroom |
On Tuesday the bricks arrived, but they are not the same colour.
Wednesday the brickies turn up. I go out to site on Wednesday afternoon thinking all of the brick work would have been finished, but it isn't. They have run out of bricks AGAIN.
They finished the front of the garage, one side and the front of the balcony and above the front door. Instead of using the different coloured bricks on the balcony and the garage ( these will be done in moroko, so you won't see the colour of the bricks) they used the correct colour bricks on these to spots and used the different coloured ones above the front door. Around the front door should be face bricks, but now there is the two different colours. Our SS told us they can be colour matched and we won't be able to tell.
![]() |
| Two different bricks |
Thursday the bricks were cleaned and that makes such a big difference to the look of the house.
| Clean bricks |
| So happy with the colour of the bricks now that they have been cleaned |
Beck
Saturday, December 10, 2011
Something got done this week. (Day 87)
Well since our last post 12 days ago, we have had some action at the house.
The A/C ducting has been fixed as much as it can be. The ducting in the corners of our bedroom have to stay, but our SS has told us he will make a niche over the bed area to hide it. This I can live with, but the one in the corner of the family room had to go. This one has been put into the cavity that we had made in our walk in robe.
We had been promised brickies would work on the Wednesday, but again no one was there. Then on Thursday they also promised brickies, but again no one there. We found out later that they finished off a job on Thursday morning, went to the pub for lunch and didn't make back to work after a liquid lunch. By this point everyone has the sh#%s with the bricklayers.
Friday morning - WE HAVE BRICKIES. It was only two of them, but at least something was going to get done. These guys did the fiddly bits under the windows on the bottom level. Derrick went out to see them on Friday morning and he was told the whole crew would be there Saturday morning.
We had about 7 guys on site on Saturday morning and Monday all day.
Brick work had to stop again on tuesday, this time because we had to wait for T bar to hold up the balcony and for over the garage doors. The builder also underestimated how many bricks we would need, and we have now run out. Kurmond has another job that is using the same bricks and same batch number that had been over estimated, so we are getting those bricks to finish the job on Monday. (We hope).
The A/C ducting has been fixed as much as it can be. The ducting in the corners of our bedroom have to stay, but our SS has told us he will make a niche over the bed area to hide it. This I can live with, but the one in the corner of the family room had to go. This one has been put into the cavity that we had made in our walk in robe.
We had been promised brickies would work on the Wednesday, but again no one was there. Then on Thursday they also promised brickies, but again no one there. We found out later that they finished off a job on Thursday morning, went to the pub for lunch and didn't make back to work after a liquid lunch. By this point everyone has the sh#%s with the bricklayers.
Friday morning - WE HAVE BRICKIES. It was only two of them, but at least something was going to get done. These guys did the fiddly bits under the windows on the bottom level. Derrick went out to see them on Friday morning and he was told the whole crew would be there Saturday morning.
We had about 7 guys on site on Saturday morning and Monday all day.
Brick work had to stop again on tuesday, this time because we had to wait for T bar to hold up the balcony and for over the garage doors. The builder also underestimated how many bricks we would need, and we have now run out. Kurmond has another job that is using the same bricks and same batch number that had been over estimated, so we are getting those bricks to finish the job on Monday. (We hope).
![]() |
| Ducting put into the corner of the family room |
![]() |
| Spaces we made for the ducting that the A/C guy didn't use |
![]() |
| Ducting put into both corners of our bedroom |
![]() |
| once the ducting was moved, now we have holes in the floor that will have to be fixed |
| These are what we have been waiting for, now we just need more bricks. |
| back of the house with the bricks done |
| front of the house just need the balcony bricked up |
Today we had the eave carpenters there, they have finished most of it - just a few little bits to do. They are also doing the cladding on the outside of bedroom four and installing the cavity sliders.
| Eaves done, the space on the right needs to have the cladding done |
Sunday, November 27, 2011
Weekly Update (Day 75) More bricks and A/C rough in.
This week started the same as the last four, with nothing happening at all. Tuesday saw a change of pace, with the Brickies finally returning and the air conditioner installer arriving to make a complete mess of what should have been a simple job.
He basically came out to install all the ducting for the A/C (aka "roughing it in"), the only problem was he didn't even look at the drawings. This clown just stuck ducting in the easiest, and in some cases stupidist, places he could find. After some robust converstation with the Site Supervisor a more logical plan was devised, and a promise made that the installer would be back to do the job properly (who knows when). I would hope that the SS would have picked up this lazy work at his next visit, but I'm glad we make regular visits to pick these things up earlier rather than later.
As for the rest of the week, nothing happened again but this time due to the non-stop rain for three and a half days.
Here's hoping next week's better...again.
He basically came out to install all the ducting for the A/C (aka "roughing it in"), the only problem was he didn't even look at the drawings. This clown just stuck ducting in the easiest, and in some cases stupidist, places he could find. After some robust converstation with the Site Supervisor a more logical plan was devised, and a promise made that the installer would be back to do the job properly (who knows when). I would hope that the SS would have picked up this lazy work at his next visit, but I'm glad we make regular visits to pick these things up earlier rather than later.
As for the rest of the week, nothing happened again but this time due to the non-stop rain for three and a half days.
Here's hoping next week's better...again.
Friday, November 18, 2011
Day 66 Weekly Update
Hmmmm. This week the only work that happened was the roof installation. So over the last four weeks, we've seen an average of one day a week with Tradies. At the current rate we should be in our new home sometime in 2014. Let's see what happens next week. (insert not happy emoticon here)
Monday, November 14, 2011
We have a roof (Day 62)
Well, let me start by saying, I have not been the happiest little person the last three weeks. I was very disappointed with the lack of work done on the house. On the plus side, I got to meet our neighbour that is building the McDonald Jones across the street today. They are now ahead of us again.
So in the last three weeks we have had scaffolding go up, (1 days work) the fascias and guttering go on, (3 hours work) and the brick work done to hold up the balcony (half a day).
So we are about two weeks behind, but the SS assures us he will make it up.
The big problem was the brick layers. We had to wait for them to do the front piers before the roof could go on. So we waited and waited. We were told they would be there by the end of the week... then Monday... then Tuesday. I drove past on Tuesday morning, and still no brick layers. I got the SS's phone number from Derrick (he was sick of listening to be complain to him) and had the brickies there by 9am the next day and they were gone by 1pm. They did what they had to and went.
The tiles arrived on Wednesday 9th, and finally something was going right.
Next we were told the roof would go up on Friday. Drive past on Friday - Nobody on site NOT HAPPY.
Then the SS promised us it would go up today. As I turned the corner this morning I was holding my breath hoping that someone would be there doing something, and low and behold the roofing guys were there! This was about 8am this morning and when I went past at 2.30, the top floor was all done and it looks great.
Beck.
So in the last three weeks we have had scaffolding go up, (1 days work) the fascias and guttering go on, (3 hours work) and the brick work done to hold up the balcony (half a day).
So we are about two weeks behind, but the SS assures us he will make it up.
| Fascias and gutters. |
The tiles arrived on Wednesday 9th, and finally something was going right.
![]() |
| Front pier that holds up the balcony. |
Next we were told the roof would go up on Friday. Drive past on Friday - Nobody on site NOT HAPPY.
Then the SS promised us it would go up today. As I turned the corner this morning I was holding my breath hoping that someone would be there doing something, and low and behold the roofing guys were there! This was about 8am this morning and when I went past at 2.30, the top floor was all done and it looks great.
Beck.
Saturday, November 5, 2011
The First Stall
Well this has been the most disappointing week so far. This week the only thing that happened was the installation of the Fascias and Gutters. That job took about half a day. So in the last two weeks scaffolding was erected (one days work), and Gutters and Fascias were installed. The builder claims that the Brickies weren't available this week and no other work can progress until they have done their bit. He also assures me that he will be able to make up for lost time, so I'll give him the benefit of the doubt and see what happens next week. Sorry no photos this time, nothing's changed anyway.